A Fijian Government Department Website. How to identify?

Official website links end with .gov.fj

Government Ministries/Departments communicate via .gov.fj websites (e.g. fiji.gov.fj). Trusted websites                                                                 

Secure websites use HTTPS

Look for a lock ( ) or https:// as an added precaution. Share sensitive information only on official, secure websites.

FIJI GOVERNMENT

A Fijian Government Department Website. How to identify ?

Official website links end with .gov.fj

Government Ministries/Departments communicate via .gov.fj websites (e.g. fiji.gov.fj). Trusted websites (Coming Soon)                                                                

Secure websites use HTTPS

Look for a lock ( ) or https:// as an added precaution. Share sensitive information only on official, secure websites.

COALITION GOVERNMENT INVESTS FJD $47 MILLION INTO WATER AND WASTEWATER INFRASTRUCTURE UPGRADES FOR NADI-LAUTOKA.

Oct 3, 2024

Share

Approximately FJD $47 million will be invested by the Water Authority of Fiji for water and wastewater upgrades in the Nadi and Lautoka corridor.

This was highlighted by the Minister for Public Works, Hon. Ro Filipe Tuisawau in his address to parliament yesterday. (02.10.24)

“This is a significant investment focused on improving the redundancy and capacity of both water and wastewater systems, ensuring it can cater to existing and future demand while improving operational and regulatory compliance.”

Key ongoing projects are as follows:

Varaqe to Saru Water Treatment Plant (WTP) Pipe Works

The Varaqe Dam and Saru Water Treatment Plant infrastructure has aged significantly. To address these challenges, a robust design with improved pipe material is being implemented to enhance resiliency and water conveyance capacity. The project cost is FJD $9.70 million to be completed by December 2024.

Nagado to Nadele Trunk Mains Upgrading Works

The Nadi-Lautoka water system faces a supply-demand gap of 5.4 megalitres per day (ML/d) due to outdated infrastructure and insufficient treatment and conveyance capacity. To address these gaps, WAF is upgrading the trunk mains, which will ensure better hydraulic performance, improve redundancy, and provide flexibility in operations between Nadi and Lautoka. The project cost is FJD $8.34 million to be completed by December 2024

Upgrading Nagado Water Treatment Plant (WTP) Capacity

It originally commissioned in 1982 with a capacity of 45 ML/d, the plant now faces operational challenges, frequently processing raw water exceeding its design capacity due to increased demand. To address these, WAF is installing an additional 20 ML/d package treatment plant to increase the treatment capacity. The project cost is FJD $14.65 million to be completed by the 1st Quarter of 2025

Wastewater Infrastructure upgrades in Denarau Island

The original system was designed to serve a single hotel but has since been expanded to accommodate the growing demand from multiple hotels and other developments on the island. The pump station and rising mains are now operating at maximum capacity, especially during peak holiday seasons, resulting in frequent failures. The pump station and rising mains are now operating at maximum capacity, especially during peak holiday seasons, resulting in frequent failures. The project cost is FJD $15-20 million to be completed in 24-36 months.

The Minister also noted that WAF projects are now aligned with the Water Sector Strategy 2050 Plan.

The Water Sector Strategy 2050 is Fiji’s first national strategy that outlines the long-term vision and provide strategic direction for ensuring sustainable and resilient water and sanitation services for all citizens in the next three decades.